Hale Family Building | Project Milestones
The following is the approximate project timeline for key phases of the proposed new Hale Family Building.
- Site Prep: Ongoing – 3rd quarter 2017
- Excavation/Foundations: 3rd quarter 2017 – 4th quarter 2018
- Steel/Concrete Superstructure: 4th quarter 2018 – 3rd quarter 2019
- Building Envelop: 2nd quarter 2019 – 1st quarter 2020
- Interior Fit-out: 2nd quarter 2019 – 4th quarter 2020
- MEP Systems Start up/Testing/Inspection: 4th quarter 2020 – 2nd quarter 2021
- Opening: 3rd quarter 2021