Boston Children's at Brookline Place | Project Schedule

The project schedule below provides information for significant upcoming work for Boston Children’s at Brookline Place. This schedule is updated regularly.

Brookline Place Redevelopment Project

Brookline Place Redevelopment Project

Look Ahead Schedule

August 30, 2019

Current Phase – 3: Construction of 2 Brookline Place (2BP) and 1 Brookline Place (1BP) addition

Upcoming Activities

Weekend Work: 8/31

1 BP: None

2 BP: None

Next Week:

Monday, 9/1: Site Closed

Tuesday, 9/3 –Friday, 9/6:

Site Operations:

-Deliveries ongoing by all trades through Gates 1 and 3 – this will result in crane operations throughout the week.

-Large soil export loads.

-Multiple excavators, loaders, bulldozers on site for site earthwork.

Earthwork

2BP:

-Place granite curb at North side and prep for sidewalks.

-Last section of interior site retaining wall to be poured.

-Install Cast iron detectable warning pavers at NW corner at Pearl Street.

-Continue install of pavers at North entry under canopy.

-Install catenary light poles in site interior (crane).

Façade/Roof:

1BP:

-Roof repair work.

2BP:

-Exterior Metal Panels to be completed.

-North canopy metal framing and light fixture install.

-Exterior doors installation.

-Terracotta and rain screen finishes at loading dock area West.

-Granite base re-work to be completed.

-Level 9 Roof flashing and coping install.

-Level 4 roof parapet cap to be installed.

Building Interior / Utilities:

2BP:

-Final mechanical, electrical, plumbing systems testing.

-Final Elevator inspections.

-Flooring and wall base install.

-Loading dock lift start up.

-Insulation and jacketing in penthouse.

-Access panels to be installed.

-Air balancing and interior door inspections.

Future:

Earthwork

2BP:

-Detectable warning pavers to be installed at 2BP West drop-off area

-Catenary light poles install.

-Final tree delivery and install.

-Final soils, hardscaping, site lighting, benches and sod placement.

-Installation of site signage.

Façade/Roof:

2BP:

-Exterior Signage at SW corner. (boom lift in the street)

-North canopy aluminum panel install at soffit.

-Exterior caulking to be completed.

-Canopies completed.

-Install of awnings at South and Northeast elevations.

Building Interior / Utilities:

2BP:

-Final MEP controls and building controls to be tested for final sign off.

-Stair 1 glass door install.

-Miscellaneous specialties – bike racks, wall graphics, crash rails.

More information about Boston Children’s at Brookline Place can be found at http://www.childrenshospital.org/about-us/expansion-and-renewal/brookline-place, and photos from the site can be found here.

The Brookline Place project team mailing address is: One Brookline Place, Suite 521, Brookline, MA 02445.