As part of the Clinical Building Expansion, a two-hour firewall
will be built on each floor of the Main Building, near the lobby
areas of the Main Elevators. Construction will take three to five
days on each floor.
Work
begins April 14 on the 5th floor and will progress in the following
order of floors: 3, 1, 2, 6, 7, 8, 9, 10, 11, 4. The process is
expected to last until late June or early July.
Construction will occur during normal work hours, with the exception
of the third floor, where it will take place over several weekends
beginning April 19. The Safety Department will work with each unit
to review safety impacts and temporary directional signage will
be posted as needed.