Schedule

Please note that the dates listed below are target working dates. As the project progresses, this section will be updated to reflect completed milestones. Refer to the project Phasing Diagrams for an illustration of the changes around the site.

Phase One: Enabling Works (September 2016 – November 2016)

  • Early September 2016, Adjustments to Vehicular and Pedestrian Access; installation of protected pedestrian pathways, construction perimeter fencing extension, relocation of Hubway, traffic impact mitigation measures including signage and parking meter cover and removal along both Pearl Street and Rte. 9/Washington Street
  • Mid-September to Mid-October, Demolition of Two & Four Brookline Place; site demolition, building demolition, and in-fill site
  • Mid-October to late November, Temporary Parking Lot Construction; prepare temporary parking area, including grading, paving, lighting and parking controls
  • End of November 2016, Closure of Existing Parking Garage and Commencement of Temporary Parking Lot Operations

Phase Two: Demolition & Construction of the Parking Garage (December 2016 – February 2018)

  • December 2016, Adjustments to Vehicular and Pedestrian Access; further changes to construction perimeter fencing and pedestrian routing, partial occupancy of Pearl Street, additional parking meter removals, vehicular travel lane impacts
  • December 2016 – January 2017, Demolition of the Existing Garage
  • February 2017 – February 2018, Parking Garage Construction

Phase Three: Construction of Two Brookline Place & One Brookline Place Addition (March 2018 – early 2020)

  • March 2018 – January 2020, Two Brookline Place Construction
  • March 2018 – April 2019, One Brookline Place Addition