Project Schedule

LIke ThisLIke ThisLIke ThisLIke ThisLIke This

Boston Children's Clinical Building

Site Prep: 4th qtr 2016 – 2nd qtr 2017
Excavation/Foundations: 2nd qtr 2017 – 3rd qtr 2018
Steel/Concrete Superstructure: 4th qtr 2018 – 3rd qtr 2019
Building Envelop: 2nd qtr 2019 – 1st qtr 2020
Interior Fit-out: 2nd qtr 2019 – 4th qtr 2020
MEP Systems Start up/Testing/Inspection: 4th qtr 2020 – 2nd qtr 2021
Opening 2nd qtr 2021

Brookline Place

Demolition of buildings at 2 – 4 Brookline Place is complete 1st qtr 2016
Install temp parking lot, completes 1st qtr 2016
Demo existing garage and build new garage – 1st qtr 2016 – 2nd qtr 2018
Construction of 1 Brookline place is scheduled to complete 1st qtr 2019 and 2 Brookline place scheduled to complete 2nd qtr 2020

Existing Longwood Campus Renovation

The first phase to start the 2nd qtr of 2019 – 1st qtr of 2021.
The last phase starts after the BCCB is occupied, 2nd qtr 2021 – 4th qtr 2023.

We are grateful to have been ranked #1 on U.S. News & World Report's list of the best children's hospitals in the nation for the third year in a row, an honor we could not have achieved without the patients and families who inspire us to do our very best for them. Thanks to you, Boston Children's is a place where we can write the greatest children's stories ever told.”
- Sandra L. Fenwick, President and CEO

Boston Children's Hospital 300 Longwood Avenue, Boston, MA 02115 617-355-6000 | 800-355-7944

Close