Boston Children's at Brookline Place | Project Schedule

The project schedule below provides information for significant upcoming work for Boston Children’s at Brookline Place. This schedule is updated regularly.

Brookline Place Redevelopment Project

Look Ahead Schedule

September 21, 2018

Current Phase – 3: Construction of 2 Brookline Place (2BP) and 1 Brookline Place (1BP) addition

Upcoming Activities

Weekend Work – September 22-23:

1 BP

  • Roofing.
  • Exterior metal framing.
  • Concrete chipping.

2 BP (Friday, 9/21 – Sunday, 9/23)

  • Tower crane laydown and demobilization

Monday 9/24 – Friday 9/28:

Site Preparations / Sitework:

  • Site preparation work will be ongoing including soil excavation, prep and backfill operations.
  • Materials hoist to be completed and operational at 2BP.
  • Temporary loading dock being constructed at 2BP.
  • Deliveries ongoing by all trades through Gates 1 and 3.
  • Small crane on site for window installation at 1 BP

Building Utilities / Building Interior:

  • Under slab building utilities for 2BP.
  • Mechanical, electrical, sprinkler, and plumbing trades working on Levels 2-7 at 1BP.
  • Spray fire proofing beams and columns at 1BP.
  • Painter at 1BP.
  • Moisture mitigation continues at 1BP.

Steel / Floor Construction / Stairs:

  • Marr to continue fastening metal deck, welding, and detail work at 2BP.
  • MEP rough at 2BP.
  • Concrete pours at 2BP slab on deck continue.
  • Stairs being installed at 2BP.
  • Steel roof dunnage to be installed at 2BP.
  • Steel at North canopy to be installed at BP.

Façade/Roof

  • Sheet waterproofing at 1BP
  • Metal stud walls and building sheathing being constructed at 1BP.
  • Roofing at 1BP.
  • Window installation at 1 BP.

Future Activities

September-October:

Site Preparations:

  • Soils excavation backfill operations, soil stock piling and soils export, will be an ongoing activity.

Building Interior / Utilities:

  • Under slab building utilities will continue for 2BP.
  • Mechanical, electrical, plumbing, sprinkler rough in 1BP & 2BP.
  • Interior metal stud walls to be constructed at1BP & 2BP.
  • In-wall rough at 1BP.
  • Finish spray fireproofing at 1BP and begin in 2BP.
  • Finish moisture mitigation at 1BP and begin 2BP.

Steel Erection/Floor Construction/ Metal Stairs:

  • 2BP decking and detail to continue.
  • Concrete floors to continue through September at 2BP.
  • Metal stairs to continue for 2BP.

Façade/Roof:

  • Metal wall and parapet framing to continue at 1BP.
  • Sheathing work to continue at 1BP.
  • Waterproofing work at 1BP.
  • Punched windows installation at 1BP.
  • Roof installations at 1BP.
  • Brick veneer install at 1BP