Boston Children's at Brookline Place | Project Schedule

The project schedule below provides information for significant upcoming work for Boston Children’s at Brookline Place. This schedule is updated regularly.

Brookline Place Redevelopment Project

Brookline Place Redevelopment Project

Look Ahead Schedule

November 2, 2018

Current Phase – 3: Construction of 2 Brookline Place (2BP) and 1 Brookline Place (1BP) addition

Upcoming Activities

Weekend Work – November 3:

1 BP

  • No work

2 BP

  • No work

Monday, 11/5 Friday, 11/9:

Site Operation:

  • Deliveries ongoing by all trades through Gates 1 and 3 – this will result in crane operations throughout the week
  • Small crane on site for window installation at 1 BP
  • Soils grading around building and site utilities
  • Scaffold at South and West elevation
  • Brick delivery and laydown area at 1BP
  • Take down and removal of East temporary stair at 2BP

Façade/Roof:

1BP:

  • Roof mechanical equipment to be hoisted and set in place
  • Window installation and testing
  • Brick veneer installation
  • Parapet framing
  • Low roof installation
  • Metal panel installation at penthouse

2BP:

  • Exterior metal framing install
  • Fire stopping at South elevation facade to continue
  • Sheathing at South elevation to begin
  • Roofing installation

Structural Steel:

1BP:

  • Complete

2BP:

  • Steel terra cotta supports, beam penetrations and penthouse slab edge angle

Building Interior:

1BP:

  • Mechanical, electrical, sprinkler, and plumbing trades working on Levels 2-7 at 1BP
  • Interior shaft wall and sheathing install
  • Fire stopping and expansion joint installation

2BP:

  • Spray fireproofing beams and columns
  • Rebar/mesh and preparation for slab on grade
  • Slab on grade at stairs and elevator pads
  • Select interior metal framing levels 2-3 and penthouse
  • MEP rough installations on-going at all floors

Future Activities:

Site Preparations:

  • Soils excavation backfill operations, soil stock piling and soils export will be an ongoing activity

Building Interior / Utilities:

1BP:

  • Mechanical, electrical, plumbing, sprinkler rough installations on-going
  • Interior walls
  • In-wall rough mechanical installations
  • Equipment hoisting
  • Scaffold demobilization

2BP:

  • Mechanical, electrical, plumbing, sprinkler rough installations on-going
  • Metal stud framing
  • Spray fireproofing
  • Fire stopping
  • Equipment hoisting
  • Slab on grade to be poured
  • Begin elevator shaft install

Façade/Roof:

1BP:

  • Metal wall and parapet framing
  • Punched windows installation
  • Roof installation
  • Brick veneer installation and granite base

2BP:

  • Spray fireproofing, metal wall and parapet framing at penthouse
  • Roof installation
  • Exterior metal framing and sheathing

More information about Boston Children’s at Brookline Place can be found at http://www.childrenshospital.org/about-us/expansion-and-renewal/brookline-place, and photos from the site can be found here.

The Brookline Place project team mailing address is: One Brookline Place, Suite 521, Brookline, MA 02445.