The redevelopment of Boston Children's at Brookline Place is a complex project with many moving parts. In planning the work, the project team explored a variety of approaches to phasing and construction logistics, taking into account any potential impacts to abutters, traffic, and public safety. The approach to phasing summarized below was determined to have the least negative impact on traffic and public safety.

Phase One: Enabling Works

Phase Two: Demolition & Construction of the Parking Facility

Phase Three: Construction of 2 Brookline Place and the 1 Brookline Place Addition

Boston Children’s is so much more than a hospital—it’s a community of researchers, clinicians, administrators, support staff, innovators, teachers, patients and families, all working together to make the impossible possible. ”
- Sandra L. Fenwick, President and CEO

Boston Children's Hospital
300 Longwood Avenue, Boston, MA 02115
For Patients: 617-355-6000
For Referring Providers: 844-BCH-PEDS | 844-224-7337

Close